Sandy commuters who ride the FrontRunner could see trains arrive twice as often by 2030 under a $3.2 billion upgrade that cleared a major federal hurdle in August.
The FrontRunner 2X project would cut peak-hour waits from 30 minutes to 15 and boost off-peak service from hourly to every 30 minutes, according to the project's official website. The schedule depends on finalizing a federal grant worth $1.28 billion.
The Federal Transit Administration (FTA) announced Aug. 7 that it approved FrontRunner 2X to enter the Engineering phase of its Capital Investment Grants program. That step moves the Utah Department of Transportation (UDOT) and Utah Transit Authority (UTA) closer to a Full Funding Grant Agreement with the FTA.
The state is covering much of the remaining cost, according to Utah Business. Construction is anticipated from 2027 through 2030, subject to completion of the federal grant process, according to a UDOT press release.
What the project builds
The upgrade adds 26.1 miles of double track in 11 locations, a new station in Bluffdale, a maintenance facility and 10 new trainsets. Most of the FrontRunner runs on a single track, which limits how often trains can pass each other.
Brian Allen, FrontRunner 2X project director at UDOT, told Utah Business there is "a lot of … orchestrating that has to happen to keep the system moving." Once complete, more than half the 82-mile route between Ogden and Provo will be double-tracked.
The FTA said the project will increase the availability, frequency and capacity of commuter trains by at least 60%.
What it means for Sandy
Sandy is one of seven Utah cities with a Housing and Transit Reinvestment Zone (HTRZ), according to UTA's HTRZ page. Sandy's zone is specifically a commuter rail station application, according to the Sandy City Redevelopment Agency's HTRZ filing.
The Sandy Cairns HTRZ covers more than 25 acres in the city's downtown district and calls for 1,480 residential units, including 178 affordable units. The application states the Cairns district is directly adjacent to I-15 and would connect to the South Jordan FrontRunner Station by a planned pedestrian bridge. Over 38,000 people commute to Sandy for work daily, the application says.
Across the full FrontRunner corridor, more than 45,000 housing units are planned near stations, according to Meg Padjen, community and economic development director at the Wasatch Front Regional Council (WFRC).
Sandy City Council members and city staff attended a WFRC workshop on the long-range Regional Transit Plan on Nov. 2.
Olympics and Sunday service
Backers say the project needs to be done before the 2034 Winter Olympics. Sen. John Curtis, R-Utah, said in the Aug. 7 UDOT announcement that the project would "better-prepare our state to host the 2034 Winter Olympics."
The double-tracking could also open the door to Sunday trains. Gavin Gustafson, senior public information officer at UTA, told Utah Business that UTA uses Sundays for track maintenance that cannot happen while trains run. Once the second track is in place, "the additional capacity will create the opportunity to operate FrontRunner seven days a week," Gustafson said.
Sunday service is not guaranteed. The project does not pay for Sunday operations, and Gustafson said UTA is still working to secure that funding.